Temp. Reso. #R8730 approving the award of Invitation for Bids No. 26-024 (Re-Bid), entitled: "2 MG Storage Tank Electrical System Rehab and Upgrade Project” to the lowest, responsive and responsible bidder, A. Bernal Services, Corporation L.L.C.; authorizing the City Manager to execute the proposed agreement with A. Bernal Services, Corporation, L.L.C., in the amount of $647,694.20 and a bid alternate in the amount of $49,400.00 and approving a contingency allowance in the amount of $100,000.00 for a total project amount not-to-exceed $797,094.20. (Utilities Project Manager James Rowley and Procurement Director Alicia Ayum)
What this record is
- Amount
- $648K
- Runs until
- no end date published in this record
- Type
- bid
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- CITY COMMISSION REGULAR MEETING
- Requested by
- Utilities
- Introduced
- May 21, 2026
- On agenda
- July 8, 2026