Temp. Reso. #R8352 approving and authorizing the execution of Change Order No. 3 to the agreement with Conti L.L.C. for additional construction services related to the purchase and installation of a new reverse osmosis skid system and related expenditures; authorizing the City Manager to execute the proposed Change Order No. 3 with Conti L.L.C., in an amount not-to-exceed $195,414; and allocating an additional contingency allowance of $200,000, for a total of $395,414 to the project cost. (Utilities Senior Project Manager Eric Francois and Procurement Director Alicia Ayum)

Resolution Agenda Ready Introduced January 30, 2025

What this record is

Held by
Conti L.L.C 2 records across this site
Amount
$395K
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Conti L.L.C also holds

Temp. Reso. #R8000 approving the award of Invitation for Bid No. 23-028, entitled, “The Purchase and Installation of a New Reverse Osmosis Skid System… $7.26M Miramar, FL
Committee
CITY COMMISSION REGULAR MEETING
Requested by
Utilities
Introduced
January 30, 2025
On agenda
March 20, 2025

Where it was heard