#R8288
Temp. Reso. #R8288 approving Change Order No. 1 to the existing agreement with the Stout Group, L.L.C., in the additional amount of $219,608 to complete Milling and Resurfacing, Sidewalk ADA Upgrades and Drainage Apron Installation BC-MIRAM-FY2020-00003 - Surtax Project. (Senior Engineering Manager Marilyn Markwei and Procurement Director Alicia Ayum)
What this record is
- Held by
- Stout Group, L.L.C 2 records across this site
- Amount
- $220K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Stout Group, L.L.C also holds
Temp. Reso. #R7951 approving the award of Invitation For Bids (“IFB”) No. 23-026 (re-bid) entitled “Milling and Resurfacing, Sidewalk ADA Upgrades and…- Committee
- CITY COMMISSION REGULAR MEETING
- Requested by
- Public Works
- Introduced
- October 31, 2024
- On agenda
- November 20, 2024