24-5418
*Approving a Change Order in the amount of $19,661.91 in accordance with Section 2-845(a) of the Code of Ordinances to Charley Toppino and Sons, Inc. for additional concrete removal services at the Richard A. Heyman Environmental Protection Facility; Authorizing any necessary budget transfers and amendments; Authorizing the City Manager to execute necessary documents upon advice and consent of the City Attorney.
What this record is
- Held by
- Charley Toppino and Sons, Inc 8 records across this site
- Amount
- $20K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Charley Toppino and Sons, Inc also holds
*Approving a Task Order from Charley Toppino and Sons, Inc. to rehabilitate eight (8) stormwater wells in the amount of $224,400.00 ($28,050.00 each) … *Approving a Task Order from Charley Toppino and Sons, Inc. to rehabilitate seven (7) stormwater wells in the amount of $196,350.00 ($28,050.00 each) … *Approving pursuant to Section 2-797(4) of the Code of Ordinances a Change Order in the amount of $32,500.00 for additional injection well rehabilitat… *Authorizing Change Order 1 to extend the Contract for the Pump Station G Rehabilitation Project with Charley Toppino and Sons, Inc. until July 23, 20… *Accepting and approving the ranking by the evaluation committee of proposals received in response to RFP 24-012 for "Professional and Related Service…All 8 records for Charley Toppino and Sons, Inc →
- Committee
- City Commission
- Requested by
- Utilities
- Introduced
- January 23, 2024
- On agenda
- February 8, 2024
- Passed
- February 8, 2024
- Enacted
- February 8, 2024
- Enactment no.
- Res 24-028