26-183
A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF HALLANDALE BEACH, FLORIDA AUTHORIZING CHANGE ORDERS TO BID # FY 2023- 2024- 07 16 32 INCH WATER MAIN REPLACEMENT WITH JVA ENGINEERING, INC. IN THE AMOUNT OF FORTY-THREE THOUSAND, FOUR HUNDRED, FORTY DOLLARS AND NINETY-SEVEN CENTS ($43,440.97), FOR A REVISED CONTRACT AMOUNT NOT-TO-EXCEED OF TWO MILLION, TWO HUNDRED, TWENTY-EIGHT THOUSAND, THREE HUNDRED, SEVEN DOLLARS AND NINETY-SEVEN CENTS ($2,228,307.97); AND PROVIDING AN EFFECTIVE DATE. (STAFF: PUBLIC WORKS DIRECTOR)
What this record is
- Amount
- $2.23M
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- City Commission
- Requested by
- Public Works & Utilities/Engineering
- Introduced
- April 22, 2026
- On agenda
- June 10, 2026