26-0251

Motion Approving a Retroactive Agreement and Increase in Contract Cost Capacity to Request for Qualification (RFQ) No. 256-11660, Stormwater Master Plan Modeling and Design Implementation Continuing Contract - Hazen and Sawyer, P.C. - $31,000,000 - (Commission Districts 1, 2, 3 and 4)

MOTION PASSED Introduced February 17, 2026

What this record is

Amount
$31.0M
Runs until
no end date published in this record
Type
rfp

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Public Works
Requested by
Public Works
Introduced
February 17, 2026
On agenda
June 16, 2026
Passed
June 16, 2026

Where it was heard

City Commission Regular Meeting Jun 16, 2026 APPROVED Pass