docketcity.com
24-333

APPROVAL OF RESOLUTION NO. 74-24 AUTHORIZING THE CITY MANAGER TO EXECUTE AN AGREEMENT WITH CDM CONSTRUCTORS, INC., FOR PHASE ONE (1) OF THE CITY OF DELRAY BEACH WATER TREATMENT PLANT PROGRESSIVE DESIGN BUILD PROJECT PURSUANT TO RFQ 2023-066, IN AN AMOUNT OF $14,982,309.00.

Resolution Passed Introduced February 22, 2024

What this record is

Amount
$15.0M
Runs until
no end date published in this record
Type
rfp
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
City Commission
Requested by
Utilities Department
Introduced
February 22, 2024
On agenda
March 5, 2024
Passed
March 5, 2024

Where it was heard

City Commission Mar 5, 2024 approved Pass