ID#26-0316
Approve a Construction Contract Amendment between the City of Clearwater and TLC Diversified, Inc. for the Lift Station 16 Pierce Street Project (20-0008-UT) to revise the contract completion date to January 14, 2026 and finalize project closeout; approve Stantec Supplemental Work Order (SWO) No. 6 in the amount of $13,200.00 for additional engineering services associated with the extended project duration and authorize the appropriate officials to execute same.
What this record is
- Amount
- $13K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Public Utilities
- Requested by
- Public Utilities
- Introduced
- March 11, 2026
- On agenda
- March 30, 2026