25-00539
Consider recommendations regarding Pavement Preservation and Preventive Maintenance; County Project No. 820800, as follows: a) Approve the specifications on file in the Public Works Department office for construction of the Fiscal Year 2024-2025 Pavement Preservation and Preventive Maintenance; b) Award the Construction Contract, in the amount of $3,540,325.00 to the lowest responsible bidder, VSS International, Inc., 3785 Channel Dr, West Sacramento, CA 95691, subject to the provision of documents and certifications, as set forth in the specifications applicable to the project, as required under California Law; c) Authorize the Director of Public Works, or designee, to approve change orders for County Project No. 820800 for a contingency amount up to $195,267.00 and supplemental items of $115,000.00, for the construction of County Project No. 820800 for a total not to exceed authorization of $3,850,592.00; d) Approve and authorize the Chair to execute a Construction Contract for County Project No. 820800, that has been reviewed and approved by County Counsel, Auditor-Controller, and Risk Manager, or their authorized representatives; and e) Determine that the project is exempt from the provisions of the California Environmental Quality Act pursuant to 14 CCR 15301(c) as the proposed project(s) consists of the operation, repair, maintenance, or minor alteration of existing public or private structures, facilities, mechanical equipment, or topographical features, involving negligible or no expansion of use beyond that previously existing, including but not limited to existing highways and streets, sidewalks, gutters, bicycle and pedestrian trails, and similar facilities, and direct staff to file a Notice of Exemption, dated May 21, 2024, on that basis.
What this record is
- Held by
- VSS International, Inc 19 records across this site
- Amount
- $3.54M
- Runs until
- no end date published in this record
- Type
- award
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
VSS International, Inc also holds
CONSIDER ADOPTING RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN PABLO (1) APPROVING AND ADOPTING THE PLANS AND SPECIFICATIONS FOR THE GIANT ROAD P… Adopt a resolution: A) Adopting plans and specifications, including conformance with prevailing wage scale requirements, for the 2026 Pavement Preserv… Adopt a Resolution to Approve and Authorize the City Manager to Award a Construction Contract to VSS International, Inc. in the amount of $6,643,120 f… Adopt a resolution increasing the Director of Public Works’ authority to execute change orders to the construction agreement with VSS International, I… Department of Transportation recommending the Board: 1) Find in accordance with Chapter 3.13, Section 3.13.030 of the County Ordinance Code, Contracti…All 19 records for VSS International, Inc →
- Committee
- BOARD OF SUPERVISORS
- Introduced
- June 12, 2025
- On agenda
- June 24, 2025
- Passed
- June 24, 2025