docketcity.com
25-712

Adopt a resolution: A) Adopting plans and specifications, including conformance with prevailing wage scale requirements, for the Lifeline Transportation Program Cycle 7 Project; and B) Authorizing the President of the Board to execute an agreement with Golden Bay Construction, Inc., for the Lifeline Transportation Program Cycle 7 Project in the amount of $1,342,680; and C) Authorizing the Director of Public Works to: 1. Execute subsequent change orders to grant time extensions for project completion and payment up to a maximum aggregate amount not to exceed $134,268, or approximately 10 percent of the agreement amount; and 2. Execute payment up to the not to exceed amount of $1,476,948 for items requiring adjustment based on unit bid prices without execution of a change order; and 3. File a Notice of Exemption for a California Environmental Quality Act Categorical Exemption.

Resolution Passed Introduced July 8, 2025

What this record is

Held by
Golden Bay Construction, Inc 2 records across this site
Amount
$134K
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Golden Bay Construction, Inc also holds

Recommendation to Authorize the City Manager to Execute an Agreement with Golden Bay Construction, Inc., for the Mecartney Road Pedestrian Crossing Im… $268K Alameda, CA
Committee
PUBLIC WORKS
Requested by
PUBLIC WORKS
Introduced
July 8, 2025
On agenda
August 12, 2025
Passed
August 12, 2025
Enacted
August 12, 2025
Enactment no.
Resolution-081369

Where it was heard

BOARD OF SUPERVISORS Aug 12, 2025 approved Pass