25-574
Adopt a resolution increasing the Director of Public Works’, or designee’s, authority to execute change orders to the construction agreement with Rodan Builders, Inc. for the San Mateo Medical Center Prevent Self Harm and Ligature Project, to increase the not-to-exceed amount of $3,806,398 by an additional $102,279, for a new not-to-exceed amount of $3,908,677.
What this record is
- Held by
- Rodan Builders, Inc 6 records across this site
- Amount
- $3.91M
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Rodan Builders, Inc also holds
Adopt a resolution increasing the Director of Public Works’, or designee’s, authority to execute change orders to the construction agreement with Roda… Adopt a Resolution Approving Addendums No. 1, No. 2, No. 3 and No. 4, and Authorizing the City Manager to 1) Award a Construction Contract to Rodan Bu… Adopt a Resolution Approving Addendums No. 1, No. 2, No. 3 and No. 4, and Authorizing the City Manager to 1) Award a Construction Contract to Rodan Bu… Authorize the Clerk of the Board to execute Notice of Completion of Contract and Acceptance of Work on Contract No. 19-14, Vietnamese American Service… Adopt a resolution increasing the Director of Public Works’ or Director’s designee’s authority to execute change orders to the Agreement with Rodan Bu…- Committee
- PUBLIC WORKS
- Requested by
- PUBLIC WORKS
- Introduced
- May 12, 2025
- On agenda
- June 10, 2025
- Passed
- June 10, 2025
- Enacted
- June 10, 2025
- Enactment no.
- Resolution-081282