docketcity.com
25-452

Adopt a resolution increasing the authority of the Director of Public Works and/or designee(s) to execute change orders to the construction agreement with Sbay Construction, Inc. for the East Palo Alto City Hall Improvements Project, to increase the not-to-exceed amount of $9,790,000 by an additional $250,000 for a new not-to-exceed amount of $10,040,000.

Resolution Passed Introduced April 24, 2025

What this record is

Held by
Sbay Construction, Inc 4 records across this site
Amount
$10.0M
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Sbay Construction, Inc also holds

Adopt a resolution: A) Adopting plans and specifications, including conformance with prevailing wage scale requirements for the Hall of Justice Court … $749K San Mateo County, CA Adopt a resolution: A) Adopting plans and specifications, including conformance with prevailing wage scale requirements, for the 1500 Fashion Island B… $278K San Mateo County, CA Accept Project as complete and authorize the Clerk of the Board to execute Notice of Completion of Contract and Acceptance of Work on Contract No. 21-… Santa Clara County, CA
Committee
PUBLIC WORKS
Requested by
PUBLIC WORKS
Introduced
April 24, 2025
On agenda
May 20, 2025
Passed
May 20, 2025
Enacted
May 20, 2025
Enactment no.
Resolution-081185

Where it was heard

BOARD OF SUPERVISORS May 20, 2025 approved Pass