Adopt a resolution authorizing the Board of Supervisors to execute an agreement with GHD for provision of final engineering, grant management, and bid- and construction-phase services for the CSA-11 Extension Project for the term of April 9, 2024 through April 8, 2027 in an amount not to exceed $614,504.

Resolution Passed Introduced March 21, 2024

What this record is

Amount
$615K
Runs until
April 8, 2027 220 days — goes back out to bid date quoted from the award document
Type
amendment
Field
Construction

See everything else expiring in this field →

Read automatically from the title of the official record. The source document below is authoritative.

Committee
PLANNING AND BUILDING
Requested by
PLANNING AND BUILDING
Introduced
March 21, 2024
On agenda
April 9, 2024
Passed
April 9, 2024
Enacted
April 9, 2024
Enactment no.
Resolution-080280

Where it was heard

BOARD OF SUPERVISORS Apr 9, 2024 approved Pass