docketcity.com
25-313

Adopt a Resolution to Approve and Authorize the City Manager to Execute a Consultant Services Agreement with BKF Engineers in the amount of $576,927 for the MacArthur / Superior Roundabout Project, Project No. 2014.0470; to Authorize the City Manager to Negotiate and Approve Individual Change Orders up to 5% (or $28,846) of the Original Contract Amount; and to Authorize the City Manager to Negotiate and Approve Cumulative Change Orders up to 10% (or $57,693) of the Original Contract Amount

Staff Report Filed Introduced June 16, 2025

What this record is

Held by
BKF Engineers 15 records across this site
Amount
$577K
Runs until
no end date published in this record
Type
amendment
Field
Professional services

Read automatically from the title of the official record. The source document below is authoritative.

BKF Engineers also holds

Contract Amendment with BKF Engineers, Inc. in the amount of $51,855 for Construction Management, Inspection and Quality Assurance Testing Services fo… $52K Hercules, CA Adopt a Resolution Authorizing the City Manager to Execute a Professional Services Agreement with BKF Engineers for the Fiscal Year 2025 Water Line Re… $681K Hayward, CA Execute a Professional Services Agreement with BKF Engineers, Inc. to provide Construction Management, Inspection and Quality Assurance Testing Servic… $193K Hercules, CA Action on Agreement with BKF Engineers for Design Professional Services for the Central Santa Clara Bicycle, Pedestrian, and Green Stormwater Improvem… Santa Clara, CA Approval of Agreement with BKF Engineers in the Amount of $470,000, to Provide Consulting Services for the East Ukiah Hills Emergency Evacuation Plann… $470K Mendocino County, CA ends Jun 30, 2026

All 15 records for BKF Engineers →

Committee
City Council
Requested by
Public Works
Introduced
June 16, 2025
On agenda
July 21, 2025
Passed
July 21, 2025
Enacted
July 21, 2025
Enactment no.
Reso 2025-096