180422
Resolution approving Modification No. 4 to Airport Contract 10071.41, Project Management Support Services for the Terminal 3 West Modernization Project, between WCME JV, and the City and County of San Francisco, acting by and through its Airport Commission, for a total amount not to exceed $14,000,000 for services, extending the term by seven months, for a total term of April 4, 2017, through April 4, 2019, pursuant to Charter, Section 9.118(b).
What this record is
- Held by
- WCME JV
- Amount
- $14.0M
- Runs until
- April 4, 2019 already ended date quoted from the award document
- Type
- amendment
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Board of Supervisors
- Requested by
- Airport Commission
- Introduced
- May 1, 2018
- On agenda
- May 1, 2018
- Passed
- August 10, 2018
- Enacted
- August 10, 2018
- Enactment no.
- 284-18