Progressive Design-Build Phase 1 Contract with McCarthy Building Companies, Inc., for the Department of Public Works Headquarters Replacement Project Located in the City of San Bernardino

Consent Passed Introduced May 12, 2026

What this record is

Held by
McCarthy Building Companies, Inc 3 records across this site
Runs until
no end date published in this record
Type
contract

Read automatically from the title of the official record. The source document below is authoritative.

McCarthy Building Companies, Inc also holds

Approves a contract with McCarthy Building Companies, Inc. for $31,000,000.00 and for 860 days for progressive design-build services to replace floori… $31.0M Denver, CO Signal Butte Water Treatment Plant (SBWTP) Expansion - Construction Manager at Risk (CMAR), Guaranteed Maximum Price (GMP) No. 2 of 2 (District 6) GMP… $112.0M Mesa, AZ
Committee
Project and Facilities Management
Requested by
Board of Supervisors Regular Meeting
Introduced
May 12, 2026
On agenda
May 19, 2026
Passed
May 19, 2026

Where it was heard

Board of Supervisors Regular Meeting May 19, 2026 APPROVED (CONSENT CALENDAR) Pass