Third Street Grade Separation at Burlington Northern and Santa Fe BNSF Railroad - Approve Agreement from Request for Proposal 2518 with DCCM Infrastructure, Inc., Riverside, for $4,516,980.16 for construction engineering and administrative services and 10 percent change order authority of $451,698.02 to be used for unforeseen circumstances for three-year term - Third Amendment to Agreement with HDR Engineering, Inc., Omaha, Nebraska, to increase contract by $473,625 for total of $3,282,267.56 for construction support services and to extend term through December 31, 2030 - Approve Amendment 4 to Transportation Uniform Mitigation Fee Program Agreement with Western Riverside Council of Governments to increase funding by $4,285,561 for total amount of $18,035,561 from Measure A and Transportation Uniform Mitigation Fee (TUMF) Accounts - Supplemental appropriations - Five affirmative votes required (Wards 1 and 2)

Public Works Agenda Ready Introduced July 24, 2026

What this record is

Held by
DCCM Infrastructure, Inc 7 records across this site
Amount
$18.0M
Runs until
December 31, 2030 4 years away date quoted from the award document
Type
rfp
Field
Construction
Compared to
$92K – $1.36M the middle half of 6 other DCCM Infrastructure, Inc contracts; median $263K — this one sits well outside that, which a longer term or wider scope will do, but is worth reading

construction contracts in CA that end within a year →
Governments publish the end date in the award. That date is when the work goes back out to bid, and it is usually stated years ahead.

Read automatically from the title of the official record. The source document below is authoritative.

DCCM Infrastructure, Inc also holds

Request for approval to execute an agreement with DCCM Infrastructure, Inc. in the amount of $222,820.00 for Professional Engineering Services in conn… $223K Harris County, TX Consider A Resolution Authorizing The City Manager To Negotiate And Execute A Professional Services Contract With DCCM Infrastructure, Inc., For The D… $1.36M Carrollton, TX Request for approval to execute an agreement with DCCM Infrastructure, Inc. in the amount of $262,695.00 for Professional Engineering Services in conn… $263K Harris County, TX Presentation, discussion, and possible action on a change order with DCCM Infrastructure, Inc. in the amount of $92,406 for additional engineering des… $92K College Station, TX Presentation, discussion, and possible action on a change order with DCCM Infrastructure, Inc. for additional design services in the amount of $73,286… $73K College Station, TX

All 7 records for DCCM Infrastructure, Inc →

Committee
City Council
Requested by
City Clerk
Introduced
July 24, 2026
On agenda
August 25, 2026

Where it was heard

City Council Aug 25, 2026 City Council Aug 25, 2026

Watch what Riverside buys

This is one award. Riverside signs them continuously, and each one names a company and a date it runs out. Say what you sell and we will email you when the next one matches.

Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.

↑ Back to top