docketcity.com
26-2158

Approve Work Order 2617219 for total capital expenditure of $484,615 from Public Utilities Electric Capital Account for Hunter Substation Circuit Tie Addition and Pole Replacement Project for Circuit 1222

Public Utilities Agenda Ready Introduced June 12, 2026
Committee
Board of Public Utilities
Requested by
Public Utilities
Introduced
June 12, 2026
On agenda
July 13, 2026

Where it was heard

Board of Public Utilities Jul 13, 2026