Award Bid SUB-875 for procurement of one substation power transformer to WEG Transformers USA, LLC, Washington, Missouri, in amount of $3,124,956 - Approve 25 percent contingency of $781,149 for Bid SUB-875 - Award Bid SUB-876 for procurement of one 15KV Metalclad Switchgear to Switchgear Power Systems, LLC, Winneconne, Wisconsin, in amount of $2,254,388 - Approve 20 percent contingency of $450,507 for Bid SUB-876 - Approve increase to Work Order 2202776 in amount of $6,611,000, for total Work Order amount from $7,080,000 to $13,691,000 from Public Utilities Substation Transformer Upgrade Capital Account

DISCUSSION CALENDAR Agenda Ready Introduced April 11, 2025

What this record is

Held by
WEG Transformers USA, LLC 2 records across this site
Amount
$13.7M
Runs until
no end date published in this record
Type
award
Field
Utilities & energy

Read automatically from the title of the official record. The source document below is authoritative.

WEG Transformers USA, LLC also holds

Approve the award of Bid 25-029, New Substation Transformer, to WEG Transformers USA LLC for an amount not to exceed $2,111,500 and for a 46-month ter… $2.11M Naperville, IL
Committee
Board of Public Utilities
Requested by
Public Utilities
Introduced
April 11, 2025
On agenda
May 12, 2025

Where it was heard

Board of Public Utilities May 12, 2025