Approve capital expenditure for Work Order 2410502 for $327,000 from Public Utilities Substation Upgrade Capital Account for La Colina Substation New Gate and Driveway Project - Recommend City Council approve Design Build Services Agreement for La Colina Substation New Gate and Driveway with Cornerstone Construction Company, Victorville, in not-to-exceed amount of $228,000 for one-year term from date specified in Notice to Proceed once issued by City - Authorize 15 percent or $34,000 change order authority for contract with Cornerstone Construction Company, Victorville, for Request for Proposal 2383 La Colina Substation New Gate and Driveway Project

Public Utilities Agenda Ready Introduced January 24, 2025

What this record is

Held by
Cornerstone Construction Company 2 records across this site
Amount
$327K
Runs until
January 24, 2026 already ended calculated from the contract term stated in the record
Type
rfp
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Cornerstone Construction Company also holds

Request for Proposal 2383 - Design Build Services Agreement with Cornerstone Construction Company, Victorville, for not-to-exceed amount of $228,000, … $327K Riverside, CA
Committee
Board of Public Utilities
Requested by
Public Utilities
Introduced
January 24, 2025
On agenda
February 24, 2025

Where it was heard