Award Bid SUB-871 to Avail Switchgear Systems, Fulton, Missouri, in amount of $2,561,551.88 for procurement of one 15KV Metalclad Switchgear for La Colina Substation - Approve 10 percent contingency or $256,155 for Bid SUB-871 - Approve increase to Work Order 2202776 in amount of $2,900,000, bringing total Work Order amount from $2,500,000 to $5,400,000 funds available in Public Utilities Substation Transformer Upgrade Capital Account

DISCUSSION CALENDAR Agenda Ready Introduced May 23, 2024

What this record is

Amount
$5.40M
Runs until
no end date published in this record
Type
award

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Board of Public Utilities
Requested by
Public Utilities
Introduced
May 23, 2024
On agenda
June 24, 2024

Where it was heard

Board of Public Utilities Jun 24, 2024