Approve capital expenditure for Work Order 2420403 in amount of $62,327,000 for design, construction, construction support, contract administration, inspection, and construction change order authority costs for Hunter Substation Replacement Project - Recommend City Council award Design-Build Agreement for Request for Proposal 1850 with Aubrey Silvey Enterprise Inc., Bremen, Georgia, in amount of $54,434,074.23 for Hunter Substation Replacement Project for term of 40 months from date specified in Notice to Proceed once issued by City - Authorize 10 percent, or $5,443,407, change order authority for contract with Aubrey Silvey Enterprise Inc., for Request for Proposal 1850 Hunter Substation Replacement Project - Authorize budget transfer of $12,512,000 from Public Utilities’ Electric Recurring projects, $15,815,000 from Public Utilities’ Electric Overhead projects, $23,350,000 from Public Utilities’ Electric Underground projects, and $10,650,000 from Public Utilities’ Electric Substation Account to Public Utilities’ Hunter Substation Replacement Account

DISCUSSION CALENDAR Agenda Ready Introduced March 8, 2024

What this record is

Held by
Aubrey Silvey Enterprise Inc 2 records across this site
Amount
$62.3M
Runs until
no end date published in this record
Type
rfp
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Aubrey Silvey Enterprise Inc also holds

Request for Proposal 1850 - Design-Build Agreement with Aubrey Silvey Enterprise Inc., Bremen, Georgia, for $54,434,074.23 plus 10 percent change orde… $54.4M Riverside, CA
Committee
Board of Public Utilities
Requested by
Public Utilities
Introduced
March 8, 2024
On agenda
April 8, 2024

Where it was heard

Board of Public Utilities Apr 8, 2024