26-84
Award a Construction Contract for the Chiles Pope Valley Road Bridge Replacement RDS 15-23 Restoration and Monitoring Project to Empire Landscaping Inc.; approve and authorize the Director of Public Works to execute Contract Change Order No. 10 to Agreement No. 240254B with Gordon N. Ball, Inc., to increase the maximum compensation from $6,246,112 to $7,724,881; and approve a Budget Amendment. (Fiscal Impact: $1,007,704; Roads Fund; Not Budgeted; Discretionary) [4/5 vote required]
- Committee
- Board of Supervisors
- Requested by
- Public Works
- Introduced
- January 5, 2026
- On agenda
- January 27, 2026