26-379
Award a Construction Contract to 2C Land and Timber Management Corp of Roseville, CA for Phase II of the Lake Berryessa Resort Improvement District Wastewater Ponds Groundwater Inflow Mitigation Project, LB 18-02; and approve Amendment No. 3 to Agreement No. 240306B with GHD, Inc. adding construction administration and inspection services for the project and increasing compensation from $312,570 to $441,649. (Fiscal Impact: $933,009 Expense; Lake Berryessa Resort Improvement District Fund; Budgeted; Discretionary)
What this record is
- Amount
- $442K
- Runs until
- no end date published in this record
- Type
- award
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Board of Supervisors
- Requested by
- Lake Berryessa Resort Improvement District
- Introduced
- February 24, 2026
- On agenda
- March 24, 2026
- Passed
- March 24, 2026
- Enactment no.
- A-240306B (LBRID) Amend. 3