26-1378
Award of Construction Contract to Rege Construction, of Cloverdale, CA in the amount of $602,598 for the “White Sulphur Spring Rd Slide Repair”, RDS 26-37 (Project 26027); and approve and authorize Amendment No. 1 to Agreement No. 260300B with ADKO Engineering, Inc. increasing the contract maximum from $366,922 to $423,176 to provide additional biological monitoring and preconstruction survey services for the Project. (Fiscal Impact: $955,000 Expense for the construction contract and other project costs; General Fund; Reallocation of Budget; Discretionary)
What this record is
- Held by
- ADKO Engineering, Inc 10 records across this site
- Amount
- $603K
- Runs until
- no end date published in this record
- Type
- award
Read automatically from the title of the official record. The source document below is authoritative.
ADKO Engineering, Inc also holds
Approve and authorize the Chair to sign Amendment No. 1 to Agreement No. 260303B with ADKO Engineering, Inc. increasing the contract maximum from $19,… Award a $1,470,376 construction contract to Cats4U, Inc. for the “Rossi Road Bridge Phase 2 Project”, RDS 25-25B; and approve and authorize Amendment … Approve and authorize Agreement No. 260201B for a contract maximum of $49,584 with ADKO Engineering Inc. for the 2026 Annual Guardrail Repair Project,… Approve and authorize Amendment No. 1 to Agreement No. 250353B with ADKO Engineering Inc, to increase the maximum compensation from $348,447 to $555,3… Approve and authorize Amendment No. 5 to Agreement No. 230084B with ADKO Engineering, Inc. increasing the maximum compensation from $588,781 to $623,7…All 10 records for ADKO Engineering, Inc →
- Committee
- Board of Supervisors
- Requested by
- Public Works
- Introduced
- June 29, 2026
- On agenda
- July 28, 2026
- Enactment no.