Approve and authorize Amendment No.1 to Agreement No. 250309B with Mead & Hunt, Inc. increasing the maximum compensation from $71,432 to $80,700 for project design services related to Project 25025 “Runway 6-24 PCC Joint Rehabilitation Project”; and approve an associated Budget Amendment to fund the added design costs and an additional $10,000 for administration costs. (Fiscal Impact $19,268 Expense; Airport Fund; Not Budgeted; Discretionary) [4/5 vote required]

Agreement Agenda Ready Introduced August 4, 2025
Committee
Board of Supervisors
Requested by
Public Works
Introduced
August 4, 2025
On agenda
August 19, 2025
Passed
December 31, 2025
Enactment no.
A-250309B Amend. 1

Where it was heard

Board of Supervisors Aug 19, 2025