24-1599
REQUESTED ACTION: Executive Director requests the following actions related to the American Canyon Leachate Line Improvement - Project No. 25801 1. Approve the Plans and Specifications for American Canyon Leachate Line Improvement Project; 2. Award Construction Contract No. 2025-03 for American Canyon Leachate Line Improvement Project to the lowest bidder, Benchmark Civil Construction, Inc. in the amount of $280,480.42; 3. Authorize the Chair to sign Construction Contract 2025-03 with Benchmark Civil Construction, Inc; 4. Authorize the Executive Director to issue change orders to the contract in accordance with Public Contract Code section 20142, in an amount not to exceed $28,048.04 per change order; and 5. Authorize the Executive Director to file a Notice of Completion with the County Recorder upon successful completion of the project.
What this record is
- Held by
- Benchmark Civil Construction, Inc 5 records across this site
- Amount
- $28K
- Runs until
- no end date published in this record
- Type
- award
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Benchmark Civil Construction, Inc also holds
Ratify and authorize the Chair to sign Agreement No. 2025-06 with Benchmark Civil Construction, Inc. for American Canyon Emergency Culvert Repair in t… Approve and authorize Agreement No. 260058B (FC) with Benchmark Civil Construction. Inc. for an annual maximum of $159,470 for services pertaining to … Authorize contract change orders to construction contracts 250364B with Benchmark Civil Construction, Inc. for the emergency slide repair at Berryessa… 1. Approval and authorization for Executive Director to execute two change orders totaling $55,720.40 with Benchmark Civil Construction, Inc. for the …- Committee
- Napa-Vallejo Waste Management Authority
- Requested by
- Napa-Vallejo Waste Management Authority
- Introduced
- September 3, 2024
- On agenda
- October 10, 2024
- Passed
- December 31, 2023