SUBJECT: Approval of Additional Contingency in the Amount of $179,197.59 for Additional Work Which is Reflected in Change Orders 2 and 3 with American Paving Co. for the Main Street Directional, Project No. CP230014 REPORT IN BRIEF Considers approving an increase to the contingency in the amount of $179,197.59 for Project No. CP230014 - Main Street Directional for the extra work reflected in Change Orders 2 and 3. RECOMMENDATION City Council - Adopt a motion: A. Approving the increase in contingency in the amount $179,197.59, for a total contingency amount of $324,068.30, which is approximately 33.55% of the original agreement amount for the extra work reflected in Contract Change Orders 2 and 3; and, B. Authorizing the City Manager to execute the necessary documents.
What this record is
- Held by
- American Paving Co 9 records across this site
- Amount
- $179K
- Runs until
- Not stated in the agenda text — the term is normally in the signed agreement, attached to the original item ↗
- Type
- amendment
- Field
- Construction
- Compared to
- $54K – $1.11M the middle half of 9 other American Paving Co contracts; median $608K
construction contracts in CA that end within a year →
Governments publish the end date in the award. That date is when the
work goes back out to bid, and it is usually stated years ahead.
Read automatically from the title of the official record. The source document below is authoritative.
American Paving Co also holds
SUBJECT: Request to Authorize the City Manager to Execute Contract Change Order No. 4 with American Paving Co. for the Additional Construction of the … Actions pertaining to the Large Park Restroom Project, Bid File 12600246 (Council District 4): 1. Adopt a finding of a Categorical Exemption per staff… Approve Contract Change Order No. 4 with American Paving Co., Inc., of Fresno, California in the amount not to exceed $629,496.67 with two hundred (20… SUBJECT: Approval of Additional Contingency in the Amount of $9,160 for Additional Work Which is Reflected in Contract Change Order No. 2 with America… Approve an Agreement with American Paving Co. for the Harris Road Bridge Emergency Repair in the Amount Not to Exceed $54,109; Approve Budget Action t…All 9 records for American Paving Co →
- Committee
- City Council/Public Finance and Economic Development Authority/Parking Authority
- Introduced
- October 9, 2025
- On agenda
- November 17, 2025
- Passed
- November 17, 2025
Where it was heard
City Council/Public Finance and Economic Development Authority/Parking AuthorityWatch what Merced buys
This is one award. Merced signs them continuously, and each one names a company and a date it runs out. Say what you sell and we will email you when the next one matches.
Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.