24-0745
Approval of Change Order Number 01 to Agreement 24-019 with Broward Builders, a California Corporation for the Jail Construction Project in the Amount of ($323,422) for a New Agreement Total of $35,535,578 for Cost Reduction Changes with No Change to the Contract Term and Appropriation of the Cost Savings to the Project Contingency
What this record is
- Held by
- Broward Builders 2 records across this site
- Amount
- $35.5M
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Broward Builders also holds
Approval of Change Order Number 01 to Agreement 24-019 with Broward Builders, a California Corporation for the Jail Construction Project in the Amount…- Committee
- General Services Agency
- Introduced
- July 8, 2024
- On agenda
- July 23, 2024
- Enactment no.
- Agreement 24-019-A1