HIGHWAY SPECIALTY COMPANY CONTRACT AMENDMENT SUBJECT: Increase Janesville Grade Guard Rail Replacement Project contract amount due to increased surface water runoff that has compromised the existing guard rails due to recent fires. FISCAL IMPACT: Funding is available within the current 2025/2026 Fiscal Year Road Fund/Budget Unit No. 122-1222 ACTION REQUESTED: 1) Increase Janesville Grade Guard Rail Replacement Project contract amount available for Contract Change Orders from $45,500 to $109,500; and 2) authorize the Director of Public Works to sign the First Amendment to Agreement; and 3) authorize Director of Public Works to execute Contract Change Orders up to a "Not to Exceed" amount of $109,500 or a total contract "Not to Exceed' amount of $560,000.

Action Item Passed Introduced September 16, 2025

What this record is

Amount
$560K
Runs until
no end date published in this record
Type
amendment

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Public Works
Introduced
September 16, 2025
On agenda
September 23, 2025
Passed
September 23, 2025

Where it was heard

Board of Supervisors Sep 23, 2025 approved Pass