ID 26-729
Approve Contract Change Order No. 03 with Katch Environmental Incorporated dba Katch General of Fresno, California in the amount of $83,886.57 increasing the total contract amount to $3,892,302.81 with 26 additional working days for the Garage 9 Renovation Project. (Bid File 12500982) (Council District 3)
What this record is
- Held by
- Katch Environmental Incorporated 2 records across this site
- Amount
- $84K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Katch Environmental Incorporated also holds
Approve Contract Change Order No. 01 with Katch Environmental Incorporated dba Katch General of Fresno, California in the amount of $203,438.20 with f…- Committee
- City Council
- Requested by
- Capital Projects Department
- Introduced
- May 18, 2026
- On agenda
- June 18, 2026
- Passed
- June 18, 2026