ID 26-22
Approve Contract Change Order No. 6 in the amount not to exceed $112,478.32, with sixty (60) additional working days, for the installation of one step-up transformer, battery controllers for the irrigation system, installation of six (6) solar lights, regrading a valley gutter, grading and compacting for the monument sign, the relocation of electrical conduits, and the installation of a bubbler, with Avison Construction Company, Inc. of Madera, CA for the Transformative Climate Communities Park at MLK Magnet Core (Les Kimber Park) Project - Project ID PW00857. (Bid File 12302905) (Council District 3)
What this record is
- Held by
- Avison Construction Company, Inc 27 records across this site
- Amount
- $112K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Avison Construction Company, Inc also holds
Approve Contract Change Order No. 1 with Avison Construction, Inc. of Madera, California in the amount of $951,860, with a not to exceed amount of $5,… Actions pertaining to the McKinley and Blythe Complete Streets Project, Bid File Number 12601327 (Council District 3) 1. Adopt a finding of Categorica… Approve Contract Change Order No. 7 in the amount not to exceed $107,830.69, with fifty (50) additional working days, for the installation of two (2) … Actions pertaining to the HAWK Pedestrian Signal at First Street & Home Avenue and Traffic Signal Improvements at Chestnut Avenue & Weldon Avenue Proj… Approve Contract Change Order No. 04 in the amount of $92,731.92, with no additional working days for overruns of various bid item quantities, additio…All 27 records for Avison Construction Company, Inc →
- Committee
- City Council
- Requested by
- Capital Projects Department
- Introduced
- December 23, 2025
- On agenda
- January 15, 2026
- Passed
- January 15, 2026