ID 26-1066
Approve Contract Change Order No. 2 with Floyd Johnston Construction Co., Inc., in the amount of $1,669,659.62, increasing the total not to exceed of $6,883,047.62, with ninety-two (92) additional calendar days for Leaky Acres Groundwater Recharge Facility Improvement Project (Bid File 12601278) (Council District 4)
What this record is
- Held by
- Floyd Johnston Construction Co., Inc 5 records across this site
- Amount
- $1.67M
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Floyd Johnston Construction Co., Inc also holds
Actions pertaining to the Leaky Acres Groundwater Recharge Facility Improvement Project (Bid File 12601278) (Council District 4): 1. Adopt a finding o… Approve Contract Change Order No. 4 with Floyd Johnston Construction Company Inc. of Fresno, California in the amount of $2,924,928.00 with one hundre… Actions pertaining to the North Avenue Sewer Trunk Main Realignment from west of State Route 99 to west of Golden State Boulevard (Bid File 12502031) … Actions pertaining to the Downtown Redevelopment Grant Water and Sewer Improvements Project (Bid File 12402356) (Council District 3): 1. Adopt a findi…- Committee
- City Council
- Requested by
- Capital Projects Department
- Introduced
- August 6, 2026
- On agenda
- August 27, 2026