ID 25-537
Approve Contract Change Order No. 4 in the amount of $1,438,210.00, with one hundred and sixty-six additional working days for additional improvements per the Phase Two and Bulletin Two Requests for Proposal with Avison Construction Company, Inc. of Madera, CA for the Transformative Climate Communities Park at MLK Magnet Core Project, now known as Les Kimber Park - Project ID PW00857. (Bid File 12302905) (Council District 3)
What this record is
- Held by
- Avison Construction Company, Inc 27 records across this site
- Amount
- $1.44M
- Runs until
- no end date published in this record
- Type
- rfp
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Avison Construction Company, Inc also holds
Approve Contract Change Order No. 1 with Avison Construction, Inc. of Madera, California in the amount of $951,860, with a not to exceed amount of $5,… Actions pertaining to the McKinley and Blythe Complete Streets Project, Bid File Number 12601327 (Council District 3) 1. Adopt a finding of Categorica… Approve Contract Change Order No. 7 in the amount not to exceed $107,830.69, with fifty (50) additional working days, for the installation of two (2) … Actions pertaining to the HAWK Pedestrian Signal at First Street & Home Avenue and Traffic Signal Improvements at Chestnut Avenue & Weldon Avenue Proj… Approve Contract Change Order No. 6 in the amount not to exceed $112,478.32, with sixty (60) additional working days, for the installation of one step…All 27 records for Avison Construction Company, Inc →
- Committee
- City Council
- Requested by
- Capital Projects Department
- Introduced
- April 9, 2025
- On agenda
- May 1, 2025
- Passed
- May 1, 2025