Approve Contract Change Order No. 4 in the amount of $1,438,210.00, with one hundred and sixty-six additional working days for additional improvements per the Phase Two and Bulletin Two Requests for Proposal with Avison Construction Company, Inc. of Madera, CA for the Transformative Climate Communities Park at MLK Magnet Core Project, now known as Les Kimber Park - Project ID PW00857. (Bid File 12302905) (Council District 3)

Action Item Passed Introduced April 9, 2025

What this record is

Held by
Avison Construction Company, Inc 27 records across this site
Amount
$1.44M
Runs until
no end date published in this record
Type
rfp
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Avison Construction Company, Inc also holds

Approve Contract Change Order No. 1 with Avison Construction, Inc. of Madera, California in the amount of $951,860, with a not to exceed amount of $5,… $952K Fresno, CA Actions pertaining to the McKinley and Blythe Complete Streets Project, Bid File Number 12601327 (Council District 3) 1. Adopt a finding of Categorica… $122K Fresno, CA Approve Contract Change Order No. 7 in the amount not to exceed $107,830.69, with fifty (50) additional working days, for the installation of two (2) … $108K Fresno, CA Actions pertaining to the HAWK Pedestrian Signal at First Street & Home Avenue and Traffic Signal Improvements at Chestnut Avenue & Weldon Avenue Proj… $1.56M Fresno, CA Approve Contract Change Order No. 6 in the amount not to exceed $112,478.32, with sixty (60) additional working days, for the installation of one step… $112K Fresno, CA

All 27 records for Avison Construction Company, Inc →

Committee
City Council
Requested by
Capital Projects Department
Introduced
April 9, 2025
On agenda
May 1, 2025
Passed
May 1, 2025

Where it was heard

City Council May 1, 2025 APPROVED ON CONSENT CALENDAR Pass