Actions related to the Terminal Expansion Project at Fresno Yosemite International Airport (Council District 4): 1. Approve Change Order No. 1 for Phase Two Construction of the Progressive Design-Build contract with Q&D Construction as part of the New Terminal Expansion project at Fresno Yosemite International Airport in an amount not to exceed $2,506,060.55 and 140 days.

Action Item Passed Introduced November 4, 2024

What this record is

Amount
$2.51M
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
City Council
Requested by
Airports Department
Introduced
November 4, 2024
On agenda
December 5, 2024
Passed
December 5, 2024

Where it was heard

City Council Dec 5, 2024 APPROVED ON CONSENT CALENDAR Pass