ID 24-1546
Actions related to the Terminal Expansion Project at Fresno Yosemite International Airport (Council District 4): 1. Approve Change Order No. 1 for Phase Two Construction of the Progressive Design-Build contract with Q&D Construction as part of the New Terminal Expansion project at Fresno Yosemite International Airport in an amount not to exceed $2,506,060.55 and 140 days.
What this record is
- Amount
- $2.51M
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- City Council
- Requested by
- Airports Department
- Introduced
- November 4, 2024
- On agenda
- December 5, 2024
- Passed
- December 5, 2024