24-1090
Adopt plans and specifications for Contract 24-03-C Elkhorn Recharge Facility (Contract 24-03-C); reject incomplete bid from West Coast Metalsmiths, LLC as non-responsive; hear and consider bid protest from apparent second low bidder, Wood Bros, Inc. 14147 18th Avenue, Lemoore, CA 93245, regarding proposed award of Contract 24-03-C to apparent low bidder, G & J Heavy Haul, 10810 Avenue 184, Tulare, CA 93274, in total amount of $4,694,440.77; award Contract 24-03-C to bidder with lowest responsible bid as determined by Board after consideration of bid protest in total amount to include base bid and some or all additive bids; and authorize Chairman to execute contract change orders for Contract 24-03-C, in excess of Director’s allowance of $210,000 pursuant to Public Contract Code 20142 for contract change orders, to a total change order limit of 7% of total compensation payable under Contract 24-03-C
What this record is
- Held by
- West Coast Metalsmiths, LLC
- Amount
- $4.69M
- Runs until
- no end date published in this record
- Type
- award
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Public Works & Planning
- Requested by
- Public Works & Planning
- Introduced
- September 17, 2024
- On agenda
- November 5, 2024
- Passed
- November 5, 2024