docketcity.com
26-1010

Department of Transportation recommending the Board: 1) Approve the continuation of perpetual agreement 427-M0810 between El Dorado County and Capital Southeast Connector Joint Powers Authority for the planning, design, and construction of the Capital Southeast Connector from Elk Grove to El Dorado Hills; 2) Approve payment of $55,000 as El Dorado County's contribution to the Joint Powers Authority operating costs for Fiscal Year (FY) 2026-27; and 3) Authorize the Purchasing Agent to process a change order to add funds to the agreement to process payment of the Joint Powers Authority operating costs for FY 2026-27. (District 1) FUNDING: Road Fund.

Agenda Item Approved Introduced June 1, 2026

What this record is

Amount
$55K
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Board of Supervisors
Requested by
Transportation
Introduced
June 1, 2026
On agenda
July 21, 2026
Passed
July 21, 2026

Where it was heard

Board of Supervisors Jul 21, 2026 Approved Pass