24-0788
Department of Transportation recommending the Board take the following actions pertaining to the El Dorado Trail - Missouri Flat Road Bike/Pedestrian Overcrossing Phase 2 Project, Capital Improvement Program No. 36109002: 1) Award Bid Schedules A and B of the Construction Contract to Westcon Construction Corp., the lowest responsive, responsible bidder; 2) Approve and authorize the Chair to sign the Construction Contract, subject to review and approval by County Counsel and Risk Management; 3) Authorize the Director of Transportation to sign an Escrow Agreement, if requested by the Contractor and in accordance with Public Contract Code Section 22300, for the purpose of holding Contract retention funds; and 4) Approve $250,000.00 of Shingle Springs Band of Miwok Indians Intergovernmental Agreement (Tribe) Funds to be added to the project. (Cont. 6/11/2024, Item 22) FUNDING: Congestion Mitigation and Air Quality (18%), Road Fund (<1%), Active Transportation Program (41%), Regional Surface Transportation Program Federal Funds - Caltrans Local Assistance (31%), Transportation Development Act (2%), Regional Surface Transportation Program Advance - Match (4%), and proposed Tribe Funds (3%). (Federal, State, and Local Funds)
What this record is
- Held by
- Westcon Construction Corp
- Amount
- $250K
- Runs until
- no end date published in this record
- Type
- award
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Board of Supervisors
- Requested by
- Transportation
- Introduced
- April 17, 2024
- On agenda
- June 18, 2024
- Passed
- June 18, 2024