Approving and authorizing the City Manager to execute a project agreement with the Maricopa Association of Governments for the Mountain Road: State Route 24 to Pecos Road project and related reimbursement. The total project cost is estimated at $13,553,887. The City is eligible for reimbursement of 70%, or up to $9,487,721, and responsible for the remaining project costs estimated at $4,066,166. This project will be funded using the Transportation Fund. (District 6) Resolution No. 12446

Resolution Agenda Ready Introduced November 6, 2025

What this record is

Amount
$9.49M
Runs until
no end date published in this record
Type
contract

Read automatically from the title of the official record. The source document below is authoritative.

Committee
City Council
Introduced
November 6, 2025
On agenda
December 1, 2025

Where it was heard