Fire Station 205 Rebuild - Construction Manager At Risk (CMAR), Guaranteed Maximum Price (GMP) No. 1 of 2 (District 2) GMP No. 1 will include temporary station site improvements, demolition of the existing fire station building, and securing the long lead electrical equipment to meet the overall timing of construction for the project. GMP No. 2 will be presented to Council at a future date for the remaining scope of work necessary to complete the project. Staff recommend awarding a contract to FCI Constructors, Inc. in the amount of $529,167.14 (GMP), and authorizing a change order allowance in the amount of $26,458.36 (5%), for a total authorized amount of $555,625.50. This project is funded by 2022 Public Safety Bonds.

Contract Agenda Ready Introduced May 29, 2025
Committee
City Council
Introduced
May 29, 2025
On agenda
June 16, 2025

Where it was heard

City Council Jun 16, 2025