Central Mesa Reuse Pipeline Plant, Construction Manager At Risk (CMAR), Guaranteed Maximum Price (GMP) No. 3 of 3 (District 1) GMP No. 3 includes the construction of the proposed Intermediate Pump Station to facilitate delivery of reclaimed water to the Gila River Indian Community (GRIC) delivery point. Staff recommend awarding a contract for this project to Garney Companies, in the amount of $15,040,620 (GMP No. 3), and authorizing a change order allowance in the amount of $752,031 (5%), for a total amount of $15,792,651. This project is funded by the Water Utility Systems Revenue Obligations.
What this record is
- Amount
- $15.0M
- Runs until
- no end date published in this record
- Type
- award
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- City Council
- Introduced
- June 20, 2024
- On agenda
- July 8, 2024