DIGESTER REHABILITATION PROJECT - 157TH AVE. WATER RECLAMATION FACILITY RECOMMENDATION: Approve the $580,294.38 contract for the Construction Contract with Felix Construction, Inc. for Digester Rehabilitation to the City of Goodyear 157th Ave. Water Reclamation Facility (WRF), and authorize the Purchase Order to be issued. PURPOSE: Approval of this contract will allow the City to proceed with construction of the Digester Rehabilitation Project at the City of Goodyear 157th Ave. WRF. The Digester Rehabilitation construction project will replace the existing lining for the north digester basin and replace existing equipment. This will provide redundancy for the solids handling facility as well as allow cleaning and inspection of the south digester basin. The project will immediately put in place corrective action in accordance with Maricopa County Environmental Services department requirements. (Brad Richards, PE, Project Manager)
What this record is
- Held by
- Felix Construction, Inc 9 records across this site
- Amount
- $580K
- Runs until
- no end date published in this record
- Type
- purchase
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Felix Construction, Inc also holds
Consider approval for the purchase and install of three (3) 18” GA Industries model 250DS/625DS AWWA C508 Sewage Surge Check Unit Valves with Felix Co… Consider approving Resolution No. 2025-126 authorizing the City Manager to execute a Construction Manager at Risk agreement with Felix Construction fo… Consider approving Resolution No. 2025-049 authorizing the City Manager to execute an emergency repair contract with Felix Construction Company for th… Approving Change Order No. 2 to Increase the Contract Amount by $230,936.77 with Felix Construction Company for the Doe Branch Discharge Improvements … Approval of a Bid Award for Whippoorwill Lift Station Electrical Improvement Project to Felix Construction Company in the Amount of $3,036,984, and Au…All 9 records for Felix Construction, Inc →
- Committee
- City Council Regular Meeting
- Introduced
- July 28, 2015
- On agenda
- August 24, 2015
- Passed
- August 24, 2015