13-5011
AMENDMENT 1, GMP 2 TO THE CM@RISK CONTRACT WITH D. L. WITHERS FOR CONSTRUCTION OF PHASE I AND II OF THE GOODYEAR OPERATIONS CENTER RECOMMENDATION: Authorize the City Manager to approve Amendment 1, GMP 2 to the CM@Risk construction contract not to exceed the Guaranteed Maximum Price (GMP) amount of $2,401,196.00 for the Goodyear Operations Center Phase I and Phase II Projects (FA1102 and FA 1201) and authorize purchase order to be issued. PURPOSE: The execution of this CM@Risk construction contract allows the City to proceed with construction of Phase I and II of the Goodyear Operations Center, which includes a secure paved and sectioned materials storage area, Public Works and Streets vehicle and equipment storage area, a materials lay down yard, a city fueling facility and vehicle wash Facility. The project also includes the infrastructure required to support these phases, as well as future phases of the Operations Center, including the new Romley Road access point to Estrella Parkway. These projects were approved and budgeted as part of the FY 10-11 and FY11-12 budget's Capital Improvement Program. (Regis Reed, Sr. Project Manager)
What this record is
- Amount
- $2.40M
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- City Council Regular Meeting
- Introduced
- April 24, 2013
- On agenda
- May 13, 2013
- Passed
- May 13, 2013