25-300
Presentation and discussion of award of contract for IFB CDBG #107-25 to Low Mountain Construction for Superstition Shadows Park Improvements in the amount of $439,804.38 plus a 10% contingency for owner controlled change orders in the amount of $43,980.44 for a total project cost not to exceed $483,784.82. Work will include new playground equipment, playground shade, and aquatic center shade at Superstition Shadows Park and be fully funded by the CDBG-RA allocation.
What this record is
- Amount
- $484K
- Runs until
- no end date published in this record
- Type
- bid
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- City Council Meeting
- Introduced
- June 4, 2025
- On agenda
- June 17, 2025