January 27, 2026 Final

Agenda — 1 item

  1. Change Order in the amount of $17,835 with PPM Consultants, Inc. for in-place tank closure. Required due to rising costs of tank fill material since original proposal and remobilization for scope change due to over-excavation and disposal of contaminated soil along piping trench required by ADEM. Allows PPM to subcontract with GrayMar Environmental to complete closure and abandonment of underground storage tanks.