- 8 Request to award Unit G-24 Southpoint Commerce Park Sewer & Water, Grade & Gravel to Carl Bowers & Sons Inc in the amount of $2,301,282.52 with a 2.8% contingency of $65,000 for a project total not to exceed $2,366,282.52.
- 7. Information Items
- 10 Change Order #4 to Staab Construction contract as part of the AWWTP Phase I Belt Filter Press Equipment Upgrades Project totaling $15,629 resulting in a decrease in contingency from $755,297 to $739,668.
- 11 Change Orders #15 and #16 to Miron Construction contract as part of the AWWTP Sludge Storage Building Addition Construction Project totaling $5,379 resulting in a decrease in contingency from $522,005 to $516,626.