23-1085
SUBJECT: Request Authorization to Waive the Competitive Bidding Process for Community Park 42 (CP-42) and Single Source the Remainder of the Work as Approved by the Merced City Council for the Construction of the Second Phase of Development at Community Park 42 (CP-42), Including the Approval of Contract Change Order No. 2 on Project Number CP220061 - Community Park 42 (CP-42) in the Amount of $1,532,539 for Additional Work REPORT IN BRIEF Staff request authorization to waive the competitive bidding requirements for CP-42 and single source the remainder of the work as approved by City Council for the construction of the second phase of development at CP-42, and request Council approve Contract Change Order No. 2 for additional site grading; installing the electrical for irrigation controls, lights, and field lights; installing storm drain and irrigation for the two extra soccer fields and landscaping, sidewalks, and basketball courts; and contract quantity adjustments in the amount of $1,532,539. RECOMMENDATION City Council - Adopt a motion: A. Waiving the City’s competitive bidding requirement as permitted by Merced Municipal Code Section 3.04.210; and, B. Approving Contract Change Order No. 2 with American Paving Co. in the amount of $1,532,539 and adding 40 working days for the change in scope of work; and, C. Authorizing the City Manager to execute the necessary documents; and, D. Authorizing the Finance Officer to make any necessary budget adjustments.
What this record is
- Held by
- American Paving Co 9 records across this site
- Amount
- $1.53M
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
American Paving Co also holds
SUBJECT: Request to Authorize the City Manager to Execute Contract Change Order No. 4 with American Paving Co. for the Additional Construction of the … Actions pertaining to the Large Park Restroom Project, Bid File 12600246 (Council District 4): 1. Adopt a finding of a Categorical Exemption per staff… Approve Contract Change Order No. 4 with American Paving Co., Inc., of Fresno, California in the amount not to exceed $629,496.67 with two hundred (20… SUBJECT: Approval of Additional Contingency in the Amount of $179,197.59 for Additional Work Which is Reflected in Change Orders 2 and 3 with American… SUBJECT: Approval of Additional Contingency in the Amount of $9,160 for Additional Work Which is Reflected in Contract Change Order No. 2 with America…All 9 records for American Paving Co →
- Committee
- City Council/Public Finance and Economic Development Authority/Parking Authority
- Requested by
- Engineering Department
- Introduced
- December 4, 2023
- On agenda
- January 2, 2024
- Passed
- January 2, 2024