R-2020-0023

Resolution accepting work of CPR, Inc. for concrete pavement patching, concrete curb & gutter, manhole adjustments and utility adjustments in Various Locations throughout City of West Allis and authorizing and directing settlement of said contract in accordance with contract terms of 2017 Project No. 26 for final payment in the amount of $500 of the $190,689.64 total project cost

Resolution Adopted Introduced January 21, 2020

What this record is

Held by
CPR, Inc
Amount
$500
Runs until
no end date published in this record
Type
contract
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Public Works Committee
Requested by
Rebecca Fleming
Introduced
January 21, 2020
On agenda
January 21, 2020
Passed
January 21, 2020