Finance Committee
Council Chambers, 6th Floor
Agenda — 12 items
- 1. Call meeting to order
- 2. Pledge of Allegiance
- 3. Roll call of membership
- 4. Approval of minutes from previous meeting
- 5 June 22nd, 2026 Meeting Minutes
- 5. Public Hearing/Appearances
- 6. Action Items
- 8 Request to add $395,500 to Community Development Budget - New & Redevelopment Projects, re: North Meadows Investment LTD Cost Reimbursement Agreement, Amendment #2.
- 7. Information Items
- 10 Contract 48-24 was awarded to Rohde Brothers for $1,612,000 with a contingency of $241,800 for the WWTP Sludge Piping & Digester Heat Exchange. Change orders were approved totaling $210,689. Final contract amount is $1,822,689 with a contingency of $31,111. Payments issued to date total $1,777,121.77. Request final payment of $45,567.23.
- 11 Contract 113-25 was awarded to RJM Construction LLC for $828,550 with a contingency of $82,800 for Community Development Interior Offices. Change orders were approved totaling $38,175.05. Final contract amount is $866,725.05 with a contingency of $82,800. Payments issued to date total $796,518.54. Request final payment of $70,206.51.
- 8. Adjournment