A resolution awarding a contract to Allied Trenchless, in the amount of $2,996,770.00, plus applicable taxes, plus a 15 percent contingency, for a total of $3,446,285.50, budgeted from the Surface Water and Wastewater Funds, for the rehabilitation of approximately 3,650 linear feet of stormwater pipe located in Buckley Gulch between North 21st and North 24th Streets and wastewater pipe located on South Tacoma Way between South “J” and South “C” Streets - Specification No. ES19-0038F. [Jordan Ennis, P.E., Project Manager; Michael P. Slevin III, P.E., Director, Environmental Services]
What this record is
- Amount
- $3.00M
- Runs until
- no end date published in this record
- Type
- award
- Field
- Utilities & energy
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- City Council
- Requested by
- Purchasing
- Introduced
- July 1, 2019
- On agenda
- July 9, 2019
- Passed
- July 9, 2019